Monthly Progress Report: Repair and Rehabilitation of Muzaffargarh Thermal Power Station
Sign inADVANCED ENGINEERING ASSOCIATES INTERNATIONAL, INC. /SGGA
The Muzaffargarh Thermal Power Station (MTPS) rehabilitation project is a key component of the USAID Energy Policy Program.
2012 · 10 pages

Abstract
The project aims to restore the station's capacity to 475 MW, with a focus on improving efficiency and reducing emissions. As of May 2012, 280 MW of capacity has been restored through the rehabilitation and replacement of equipment. The rehabilitation efforts have focused on several key areas, including the replacement of boiler super heater tubes, special cooling water treatment, and the use of fuel oil additives. The project has also involved the procurement of new equipment, including electric motors, DC storage batteries, and air pre-heater elements. The total amount allocated for the project is $15,778,195, with $4,872,500 already disbursed under the original FARA. The project has encountered some delays due to the GENCO's weak financial standing, which has impacted the procurement process. However, EPP experts have worked with USAID to redefine the reimbursement process and revise the FARA to facilitate timely payments to vendors. A new Activity Agreement and implementation letter were signed in April, allowing GENCO to access necessary funding for the project. As of May 31, 2012, a total of 13 work items have been completed, with 6 items still in progress. The total amount reimbursed so far is $4,872,500, with $2,945,723 in claims submitted to USAID/ENR for approval. The project is expected to be completed by June 30, 2013, with a revised completion date per the new Activity Agreement. The project has also involved the procurement of new equipment, including 0.4KV motors, 6.6KV motors, and protection relays. The total amount allocated for these procurements is $295,005, with $162,945 already disbursed. The project has also involved the supply, installation, commissioning, and testing of a distributed control system (DCS) for the turbine governing system and boiler turbine auto regulation system. The project's progress is being closely monitored, with a focus on ensuring timely completion and adherence to specifications. The project's success will have a significant impact on the country's energy sector, improving efficiency and reducing emissions.
Connected topics
Classification
USAID DEC