Emergency shelter rehabilitation project : Kosovo -- final report : September 1-December 31,1999
Sign inCONCERN WORLDWIDE
Final report of the contractor, Concern Worldwide, on a project (9/1/99-12/31/99) to provide emergency shelter rehabilitation to ensure that 700 vulnerable families in the Kosovo Province of the former Yugoslavia have sufficient housing throughout the 1999/2000 winter.
2000

Abstract
Concern Worldwide completed emergency shelter rehabilitation in 9 urban areas and 18 peri-urban villages in Peje municipality, carrying out a total of 697 structural assessments. The Concern shelter kit consists of materials for constructing a reinforced plastic-covered roof structure and the winterization of one room in each house. In addition, further warm room kits were distributed to 342 families. (As agreed with USAID/Office of Foreign Disaster Assistance [OFDA], any surplus funding on construction materials was used to purchase extra warm-room materials). By December 31, Concern had distributed roofing materials and warm-room kits to 685 beneficiaries. A further 6 roofing packages and warm room kits were distributed in January. Distribution of 342 additional warm rooms to vulnerable families also took place in January. By December 31, a total of 596 roofs had been constructed, 310 by the Concern labor contractor and 286 by beneficiaries themselves. Construction continued through February. By the end of February, a total of 610 roofs were completed. Other beneficiaries who received materials are storing the materials in order to use them for reconstruction in the spring. (Author abstract, modified)
Connected topics
Classification
2001USAID DEC