Abstract
VARIATION OF ISRAEL DESIGN ENGINEERING (IDE) PROCESS UTILIZED (TECHNICAL DETAILS-PROP); IDE ALSO RESPONSIBLE CONTRACTOR FOR FINAL DESIGN, CONSTRUCTION, TESTING, FACILITY MANAGEMENT OF INTERMEDIATE & FINAL MODULES. PRELIMINARY 1 MILLION GALLONS PER DAY (MGD) AT ELAT OPERATIONAL. FEASIBILITY STUDIES FOR 11 MGD FACILITY APPROVED. $55160000 BUDGET FOR CONSTRUCTION, TESTING, OPERATION & 5 YEARS MAINTENANCE OF 10 MGD PLANT AT ASHDOD TO CONVERT SEAWATER TO FRESH WATER FOR 42000 POPULATION. DESALTING PROCESS APPLICABLE TO WATER SHORT LANDS WORLDWIDE. 50 MEGAWATT POWER STATION ALSO IMPROVED IN PROJECT.