Engineering Support Program (ESP) Activity 006 Salang Tunnel Substation Monthly Report No. 55
Sign inDA AFGHANISTAN BRESHNA SHERKAT
The Salang Tunnel Substation project is a 220/20 kilovolt (kV) substation and a 20 kV distribution network designed, supplied, tested, and commissioned by Da Afghanistan Breshna Sherkat (DABS) as part of the USAID supported Power Transmission Expansion and Connectivity (PTEC) program.
2021 · 26 pages

Abstract
The project involves the design, supply, testing, and commissioning of a substation and distribution network in the Salang Tunnel area. The project was awarded under DABS Contract No. DABS-94-ICB-023. The contract was signed between DABS and the contractor, Tetra Tech, with a period of performance (POP) of approximately 12 months. The project is funded by the United States Agency for International Development (USAID) and is expected to improve the reliability and efficiency of the power transmission system in the Salang Tunnel area. The project involves several key components, including the design and supply of a 220/20 kV substation, a 20 kV distribution network, and associated transmission lines. The substation will be equipped with a 220 kV Bay Control Unit (BCU) and a 20 kV Medium Voltage (MV) switchgear. The distribution network will consist of a 20 kV transmission line and a 20 kV distribution line. The project is being implemented by Tetra Tech, with the support of several subcontractors, including Construction Management Services (CMS) and Engineering Submittals. The project is expected to be completed within the specified period of performance, with a total budget of approximately $1.5 million. The project has several key milestones, including the completion of the design and supply of the substation and distribution network, the testing and commissioning of the substation and distribution network, and the completion of the project within the specified period of performance. The project is expected to improve the reliability and efficiency of the power transmission system in the Salang Tunnel area, and will contribute to the overall goal of increasing access to reliable and efficient power transmission in Afghanistan. The project is being monitored and evaluated by the USAID supported Power Transmission Expansion and Connectivity (PTEC) program, which is responsible for ensuring that the project is implemented in accordance with the contract requirements and that the project is completed within the specified period of performance. The project is also being monitored and evaluated by the Special Inspector General for Afghanistan Reconstruction (SIGAR), which is responsible for ensuring that the project is implemented in accordance with the contract requirements and that the project is completed within the specified period of performance. The project has several key risks, including the risk of delays in the completion of the project, the risk of cost overruns, and the risk of non-compliance with the contract requirements. The project is being implemented in a challenging environment, with several challenges, including the lack of infrastructure, the lack of skilled labor, and the lack of equipment. The project is expected to be completed within the specified period of performance, with a total budget of approximately $1.5 million. The project is expected to improve the reliability and efficiency of the power transmission system in the Salang Tunnel area, and will contribute to the overall goal of increasing access to reliable and efficient power transmission in Afghanistan.
Classification
USAID DEC