USAID DEC
The Peshawar-Torkham road is a vital component of National Highway (N-5), connecting Pakistan with Afghanistan at the Torkham border.
2015 · 126 pages

Abstract
This road plays a crucial role in the nation's economic activities and provides timely logistical support to security agencies deployed in Khyber Agency. The project, "Strengthening & Improvement of Peshawar Torkham Road," is funded by the United States Agency for International Development (USAID) with a grant amounting to USD 67 million. The project is implemented by the FATA Secretariat as the project proponent through Frontier Works Organization (FWO) as the EPC (Engineer, Procure, and Construct) contractor. The 46-kilometer Peshawar-Torkham road has been divided into multiple sections for design and construction purposes due to site-specific conditions such as live traffic corridors, hilly terrain, safety, and security restrictions. The project commenced on October 15, 2012, with an initially agreed completion date of December 31, 2014, as per Article 4 of the Agreement. The project's progress is monitored through monthly reports, which provide detailed information on the activities undertaken and the milestones achieved. The reports highlight the challenges faced by the contractor, including the completion of Section I, II, and III, the process of PC-1 approval, maintaining traffic on diversions/divertors, and environmental compliance. The civil works section-wise progress status indicates that significant progress has been made in all sections. In Section I, the cumulative milestone-wise progress status shows that 11.00% of the work has been completed. The physical progress status in Section I indicates that the culverts' physical progress status is 25%. In Section II, the cumulative milestone-wise progress status shows that 27.50% of the work has been completed, while the physical progress status indicates that the pavement construction physical progress status is 29%. The project also involves the construction of bridges, with the cumulative milestone-wise progress status of Bridge (KM: 09+560) showing 40% completion. The physical progress status of Bridge (KM: 09+560) indicates that 40% of the work has been completed. The project's environmental compliance monitoring is also being carried out, with regular reports submitted to the project authorities. The project's progress is also being monitored through the mobilization of M&E staff, coordination meetings, and joint site visits. The project photographs are also being maintained to document the progress of the project. The project's overall progress is satisfactory, with significant progress made in all sections.
Connected topics
Classification