HORN INTERNATIONAL RELIEF AND DEVELOPMENT ORGANIZATION
The Construction Monthly Progress Report for the period of July 01- July 31, 2015, details the progress of the Arraba Well Pump Station project.
2015 · 164 pages

Abstract
The project is part of the Water, Sanitation, and Hygiene (WASH) program in the West Bank and Gaza. The project aims to improve access to safe drinking water for the local population. The project is being implemented by International Relief and Development, Inc. (IRD) under the supervision of the Palestinian Water Authority. The project involves the rehabilitation of the Arraba Well Pump Station, which includes the installation of a new pump, electrical and mechanical systems, and the construction of a new water storage tank. The report highlights the progress made during the reporting period. The Safety Plan and Environmental Monitoring and Mitigation plan were approved by the Construction Management Committee (CMC). The site office was equipped with a first aid kit and fire extinguishers. Safety meetings were conducted with the IRD subcontractor to improve the safety program and increase awareness of the subcontractor's responsibilities for the health and safety of their workers. The report also details the progress made in the construction activities. The concrete barriers and fence around the manholes, pump cover protection, and concrete barriers around the excavated seepage pit were completed. The site was cleaned and maintained regularly. The project is still behind schedule, with a 52.48% planned percentage complete compared to the 40.48% actual percentage complete. However, the project team is closely monitoring the activities and is confident that the delays will be recovered with the additional resources and extended working hours. The report also includes a summary of the progress made in the construction activities, including the completion of the electrical and mechanical systems, and the installation of the new pump. The project is expected to be completed within the performance time, and the IRD team is working closely with the Palestinian Water Authority to ensure the successful completion of the project. The report includes several attachments, including the list of materials and equipment delivered to the site, the progress summary table, and the photos of the construction activities. The report concludes that the project is making progress, and the team is working to recover the delays and complete the project within the scheduled time. The project's overall status is still behind schedule, but the team is confident that the delays will be recovered with the additional resources and extended working hours. The project is expected to be completed within the performance time, and the IRD team is working closely with the Palestinian Water Authority to ensure the successful completion of the project. The report highlights the importance of safety and environmental measures on site, and the team is working to ensure that all necessary measures are in place to prevent accidents and environmental damage. The project's progress is summarized in the progress summary table, which shows the planned and actual percentage complete for each activity. The table demonstrates that the project is still behind schedule, but the team is working to recover the delays and complete the project within the scheduled time. The report concludes that the project is making progress, and the team is working to recover the delays and complete the project within the scheduled time. The project's overall status is still behind schedule, but the team is confident that the delays will be recovered with the additional resources and extended working hours.
Connected topics
Classification